Emerson Exchange 365
Search
User
Site
Search
User
Replies
0 replies
Subscribers
5479 subscribers
Views
6267 views
Users
0 members are here
Recent DeltaV Community Connect Discussions
gbilly
27 Aug 2024 6:08 PM
Assigned new DO Isolated VAC & when testing on false in logic at charm still reading present VAC?
0 Replies
TPatterson
26 Aug 2024 7:54 PM
cut-out dimensions of DeltaV touchscreen workstation
0 Replies
TreyB
23 Aug 2024 7:04 PM
Modbus Serial card, Diagnostic Data
0 Replies
TreyB
22 Aug 2024 10:17 PM
Live, database backup
3 Replies
Benji_Kidmose
19 Aug 2024 10:58 PM
DeltaV Live - Tabs
6 Replies
<
>
Similar Posts
Downloading a Running Phase on Redundant Controller
Downloading to a running Unit Phase - Redundant Controller Warning
Risk of Downloading a Redundant M-Series Serial I/O Card on a Running Process
How to detect if DeltaV Operate is running
DeltaV Operate Run/Configure Parameter
Share
DeltaV operate(Run) redundancy
Dear Expert
We are using deltaV 10.3 in our plant and our deltaV system use redundant MQ controller. If primary controller fail then secondary controller switch over and taking all responsibility. But our deltaV operate (Run) system not switching. My question is deltaV use software redundancy for graphics redundancy ?? Please guide me to overcome this problem.
Regards
Krishna