Hi
I'm trying to confirm how to carry out a manual switchover of a pair of redundant batch executives before updating / patching etc.
This is required to be carried out on a live plant, so I need to keep interruptions to production to a minimum.
If I understand correctly, this should be as simple (!):
Am I being too simplistic? Are there any pitfalls / precautions?
Thanks for any advice.
Hi Colin. You're almost there! I've added a couple of notes to your sequence from the best practices I've developed for the systems I manage in New England.
Best regards.
Ray