Update: Went ahead and commissioned the switches and the "wizard" creates the modules.
I'm ready to commission a switch using the "Network Device Command Center" in DeltaV 13.3, and it's prompting me for a "switch name" - name to be assigned to the switch module . . . must be a valid DeltaV module name.
I just wanted to confirm - I don't need to pre-build a module that this switch will point to, the command center "builds" it when the switch is commissioned. It just needs a valid module name. (A default or a suggestion would be helpful here).
(You don't . . . )
Thanks,
John
In reply to Matt Stoner:
Andre Dicaire
In reply to Andre Dicaire:
In reply to ryanscofield: